ANALYSIS OF PROJECT TIME AND COST CONTROL WITH CPM, PERT AND CRASHING PROJECT METHODS IN SHOP BUILDING PROJECTS AT CV. MENTARI PERMAI

Authors

  • Rosalinda Rosalinda
  • Nizmah Nizmah
  • Suko Ari R
  • Makmur Makmur
  • Dian Rarasanti

DOI:

https://doi.org/10.37481/sjr.v6i1.622

Keywords:

Project Management, Critical Path Method (CPM), Program Evaluation and Review Technique (PERT), Crashing Project

Abstract

Delays in completing the Kelapa Dua shop-house construction project at CV. Mentari permai is a problem that often arises and affects the overall project work. The purpose of this research is to determine the critical path, calculate the costs incurred in the construction of the Kelapa Dua shop-house construction project with the duration of the initial and accelerated work and calculate the percentage of achievement of the shop construction project at CV. Mutia Enchantment of Nature. To overcome these delays, several control methods are used in project management. The methods used in this research are the Critical Path Method, PERT (Program Evaluation and Review Technique) and the Crashing Project. The results of the CPM planning method analysis obtained the project completion time for 91 days from the initial duration of 154 days. Whereas in reality the CPM method, the project completion time is 101 days from the initial duration of 167 days. In the PERT method, the project completion time is 107 days from a duration of 181 days with a probability of completion of 0.62%. And in the crashing project there is an acceleration of the completion duration for 9 days with an increase in costs of Rp. 26,545,194 and a total cost of Rp. 506,613,766.

References

Almatroushi, H., Hariga, M., As' ad, R., & Al-Bar, A. (2020). The multi resource leveling and materials procurement problem: an integrated approach. Engineering, Construction and Architectural Management, 27(9), 2135-2161.

Argiansyah, Y., Susetyo, B., & Fahmi, F. (2021). Key Success Factor Analysis in Application of Manual Pert Method in Rail Road Construction.

Banihashemi, S., Khalilzadeh, M., Shahraki, A., Malkhalifeh, M. R., & Ahmadizadeh, S. (2021). Optimization of environmental impacts of construction projects: a time–cost–quality trade-off approach. International Journal of Environmental Science and Technology, 18(3), 631-646.

Cha, J., Newman, M., & Winch, G. (2018). Revisiting the project management knowledge framework: Rebalancing the framework to include transformation projects. International Journal of Managing Projects in Business.

Dai, C. Q., Li, C., Fu, S., Zhao, J., & Chen, Q. (2020). Dynamic scheduling for emergency tasks in space data relay network. IEEE Transactions on Vehicular Technology, 70(1), 795-807.

Do, S. T., Nguyen, V. T., Tran, C. N., & Aung, Z. M. (2022). Identifying and evaluating the key claim causes leading to construction delays. International Journal of Construction Management, 1-13.

Hansen, L. K., & Svejvig, P. (2022). Seven Decades of Project Portfolio Management Research (1950–2019) and Perspectives for the Future. Project Management Journal, 53(3), 277-294.

Izmailov, A., Korneva, D., & Kozhemiakin, A. (2016). Effective project management with theory of constraints. Procedia-Social and Behavioral Sciences, 229, 96-103.

McDonough III, E. F. (2000). Investigation of factors contributing to the success of cross?functional teams. Journal of Product Innovation Management: An International Publication of the Product Development & Management Association, 17(3), 221-235.

Nahendra, N., Daulay, I. N., & Paramitha, A. (2022). The optimization of Gebe Airport project using PERT and CPM method. Operations Management and Information System Studies, 2(4), 208-218.

Natawidjana, R., & Nurasiyah, S. (2020). Study of labor cost escalation in delay projects. Paper presented at the Journal of Physics: Conference Series.

Pandiyan, S., Lawrence, T. S., Sathiyamoorthi, V., Ramasamy, M., Xia, Q., & Guo, Y. (2020). A performance-aware dynamic scheduling algorithm for cloud-based IoT applications. Computer Communications, 160, 512-520.

Rauzana, A., & Dharma, W. (2022). Causes of delays in construction projects in the Province of Aceh, Indonesia. PloS one, 17(1), e0263337.

Ruslan, W. (2019). Project Management: Network. Atma Jaya Catholic University of Indonesia publisher.

Sitanggang, N., Simarmata, J., & Luthan, Putri Lynna A. (2019). Introduction to Project Management Concepts for Engineering. Medan: Our Writing Foundation.

Suwarni, Princess Endah; Prasetio, D. (2019). Optimization of project time and costs using the Cpm and Pert method in the ABC Condotel project. Industrika, 3(1), 9–23.

Wen, F., Zhao, Y., Zhang, M., & Hu, C. (2019). Forecasting realized volatility of crude oil futures with equity market uncertainty. Applied Economics, 51(59), 6411-6427.

Yu, F., Chen, X., Cory, C. A., Yang, Z., & Hu, Y. (2021). An active construction dynamic schedule management model: using the fuzzy earned value management and BP neural network. KSCE Journal of Civil Engineering, 25(7), 2335-2349.

Iswardani, W. (2021). Hydroponic Vegetable Production Planning at Plantation Parung Farm Bogor. AKADEMIK: Jurnal Mahasiswa Sain & Teknologi, 1(1), 8-15.

Indra, W. (2021). Detection of Gen C/EBP? Encodes the Meat Quality. AKADEMIK: Jurnal Mahasiswa Sain & Teknologi, 1(1), 24-32.

Downloads

Published

2023-01-01

How to Cite

Rosalinda, R., Nizmah, N., Ari R, S. ., Makmur, M., & Rarasanti, D. . (2023). ANALYSIS OF PROJECT TIME AND COST CONTROL WITH CPM, PERT AND CRASHING PROJECT METHODS IN SHOP BUILDING PROJECTS AT CV. MENTARI PERMAI. SCIENTIFIC JOURNAL OF REFLECTION : Economic, Accounting, Management and Business, 6(1), 85-94. https://doi.org/10.37481/sjr.v6i1.622